Moving premises is the one time you get to build your IT properly from scratch. Most businesses spend that opportunity on carpet colours and discover the cabling problem in week two.

None of what follows is expensive during a fit-out. All of it is expensive afterwards, because afterwards means walls, ceilings and someone's desk.

Before you sign

Check what internet you can actually get

Not what is advertised for the suburb — what is available to that specific address, in that specific building. We have watched a business sign a lease and then wait eleven weeks for a service the building could not deliver without new lead-in works. Check the address, get it in writing, and find out who owns the building's lead-in.

Find the comms room before you agree the floor plan

You need somewhere for a rack that is secure, ventilated, has power, and is reasonably central. A cupboard in the far corner with no airflow means either expensive fibre runs or equipment cooking itself quietly all summer. In a Queensland summer, ventilation is not optional.

Ask what the last tenant left

Sometimes there is usable Cat6 in the walls and a serviceable rack. Sometimes there is a bird's nest of unlabelled Cat5e from 2009 that will not carry what you need. Worth twenty minutes with a torch before you budget as though either is true.

During the fit-out

Run more cable than you need

The cable is cheap. The labour to pull it is most of the cost, and it is the same labour whether you run one outlet or three. Two data points per desk minimum, and run them to places you do not currently plan to use — the meeting room wall, the reception desk, above the ceiling where access points will go.

Every business we work with adds desks. None of them add walls to run new cable through.

Cat6A, and here is why

For new installs the price difference over Cat6 is marginal. It gives headroom for multi-gig, and it delivers Power over Ethernet more comfortably over distance — which matters because your access points, cameras and door controllers are all going to want PoE. You are cabling for the next ten years, not this year's switch.

Plan Wi-Fi properly, or at least plan it

"Put an access point in the middle" is not a plan. Coverage depends on the building — concrete, glass partitions and plasterboard behave completely differently, and a warehouse is not an office. Cable to the ceiling locations during the fit-out even if you install fewer APs initially. Cabling to a ceiling with the tiles out costs a fraction of what it costs afterwards.

The mistake that costs the most

Letting the electrician run the data cabling because they are already on site. Data cabling is a different trade with different standards, different testing and different termination practice. It usually works well enough to pass a casual test and then produces intermittent faults for years — the kind nobody can reproduce and everybody blames on the internet.

Label everything, and get the test results

Every outlet labelled, matching the patch panel, with a written schedule you keep. Insist on certification test results for each run. If a cabler will not provide them, that tells you something useful.

Before you move in

  • Get the internet connected early — two weeks before move day, not on it. If it slips, you find out while you still have the old office
  • Port the phone numbers with lead time. Number porting takes longer than anyone expects and cannot be rushed on the day
  • Set up and test the network before the desks arrive, while you can still reach everything
  • Move the server last, or move it to the cloud first. A physical server in a car on a Saturday is a risk you can often design out entirely
  • Plan the first morning. Someone on site who can fix things while thirty people try to print at once

The short version

  • Confirm internet availability at the exact address before signing
  • Secure, ventilated, central comms room — agree it with the floor plan
  • Over-cable while walls are open; labour is the cost, not the cable
  • Cat6A for PoE headroom and future speed
  • Use a data cabler, not the electrician, and demand test results
  • Internet and number porting need weeks of lead time, not days

Get these right and moving day is boring. Boring is the goal.